Cost to Remove Two Layers of Shingles

A second layer of shingles adds $0.75 to $1.25 per sq ft in our Greater Victoria model: $900 to $1,500 on a two-storey home, $1,800 to $3,000 on a rancher.

Greater Victoria dataIndependent, no contractor commissions on adviceSources and methodology on every page

Quick answer

Removing a second layer of shingles adds $0.75 to $1.25 per square foot of roof in our Greater Victoria pricing model, which is $900 to $1,500 on a 2,000 sq ft two-storey home and lifts its asphalt replacement from $6,900 to $12,600 to $7,800 to $14,100 before GST. On a 2,000 sq ft rancher with twice the roof the extra layer adds $1,800 to $3,000, and a third layer doubles those figures again. Canadian guides quote $1,000 to $3,000 for removal and disposal as a lump sum. The cost is labour and bin weight: old shingles are heavy, and a second layer often hides a first layer of cedar.

Extra tear-off per layer
$0.75–$1.25 / sq ft of roof
Two layers, 2,000 sq ft two-storey
$7,800–$14,100 (adds $900–$1,500)
Two layers, 2,000 sq ft rancher
$15,000–$27,000 (adds $1,800–$3,000)
Three layers, 2,000 sq ft rancher
$16,800–$30,000 (adds $3,600–$6,000)

Next step: About 60 seconds. Greater Victoria pricing. No sign-up.

Calculate My Roof Cost

Key facts

Extra tear-off per layer
$0.75–$1.25 / sq ft of roof
Our pricing model (estimate)
Two layers, 2,000 sq ft two-storey
$7,800–$14,100 (adds $900–$1,500)
Our pricing model (estimate)
Two layers, 2,000 sq ft rancher
$15,000–$27,000 (adds $1,800–$3,000)
Our pricing model (estimate)
Three layers, 2,000 sq ft rancher
$16,800–$30,000 (adds $3,600–$6,000)
Our pricing model (estimate)
Canadian guides, removal lump sum
$1,000–$3,000
Source: Green Building Canada

Greater Victoria context

Layered roofs are an older-home problem, and Greater Victoria has the oldest housing in BC. In the decades when tipping fees were low and labour was cheap, many James Bay, Fernwood, Oak Bay and Esquimalt homes had asphalt laid straight over the original cedar shingles, and some were covered a third time in the 1980s. A roofer walking a 1920s Fairfield roof today will often find asphalt over asphalt over cedar over skip sheathing, which means the tear-off exposes gaps in the deck that need plywood before anything new goes on.

The 1960s to 1980s suburbs have the more common two-layer case: a second asphalt layer installed over the first in the 1990s to save a few thousand dollars. Gordon Head, Colwood and Sidney ranchers with a lumpy, wavy look at the eaves are the giveaway. Disposal is at the Hartland landfill in Saanich, priced by weight, and a double layer on a rancher can fill two bins where one would do.

Extra tear-off cost by number of layers and home type, asphalt (our estimate, before GST)
HomeRoof areaOne layer (included)Two layersThree layers
1,500 sq ft, two storeysabout 900 sq ft$5,200–$9,400$5,900–$10,600$6,500–$11,700
2,000 sq ft, two storeysabout 1,200 sq ft$6,900–$12,600$7,800–$14,100$8,700–$15,600
2,000 sq ft, one storeyabout 2,400 sq ft$13,200–$24,000$15,000–$27,000$16,800–$30,000
2,500 sq ft, one storeyabout 3,000 sq ft$16,500–$30,000$18,700–$33,700$21,000–$37,500

Moderate pitch, sound decking, easy access. Cedar under asphalt and skip sheathing that needs plywood are priced separately.

How to tell how many layers you have

Look at the edge of the roof at the eave or rake from a ladder or with binoculars from the ground. One layer shows a single thickness of shingle over the drip edge; two layers show a doubled step. Inside the attic, look at the underside of the deck near the eave: if you see cedar shingles between the boards, there is cedar under the asphalt. A roofer will confirm by lifting a shingle at a corner. Do not walk the roof yourself to check; the information is available from the edge.

  • Doubled or lumpy edge at the eaves
  • Wavy shingle lines across the slope
  • Cedar visible between deck boards from the attic
  • Roof looks thicker than the neighbour's at the ridge

Why the second layer costs what it does

Tearing off is manual: shovels, forks and bars, then loading and carrying to the bin. A second layer roughly doubles that labour and doubles the weight to be lifted and tipped. Old asphalt is heavy, around 200 to 250 pounds per square per layer, so a 24-square rancher with two layers has five tons of shingles to move. Our $0.75 to $1.25 per sq ft covers the labour and the extra disposal; Canadian guides express the same cost as a $1,000 to $3,000 lump sum for removal.

Ready to see your own number? About 60 seconds. Greater Victoria pricing. No sign-up.

Calculate My Roof Cost

What a second layer often hides

The surprise under a second layer is rarely the layer itself. It is what the first layer was laid on: cedar shingles on skip sheathing (spaced boards) in pre-1950 homes, which cannot take a new shingle roof without a plywood overlay, or decking softened by decades of moisture trapped between layers. In our model plywood over skip sheathing or replacement of rotten decking is priced at $7 to $10 per sq ft of the area involved, and a quote on a layered old roof should carry a decking allowance of $500 to $2,500 at minimum.

Can you add a third layer instead?

Most Greater Victoria roofers will not, and a layered roof is one of the few cases where the answer is easy. Every layer adds weight to rafters designed for one, traps heat and moisture, hides decking problems, and makes the flashings at chimneys and walls impossible to do properly. Manufacturer warranties usually require installation on a clean deck. Whether the building code or your municipality sets a hard limit is something to confirm with the building department; the practical answer from the trade is tear off.

Frequently asked questions

How much does tear-off and disposal add to a roof replacement?

One layer is included in our rates. A second layer adds $0.75 to $1.25 per sq ft of roof, so $900 to $1,500 on a two-storey 2,000 sq ft home and $1,800 to $3,000 on a rancher. Canadian guides quote $1,000 to $3,000 for removal as a lump sum.

Does roof replacement cost include removing the old roof?

In our model and in most Greater Victoria quotes, one layer of tear-off and disposal is included. Extra layers are itemised. Always confirm layers and disposal appear on the quote.

Can you put new shingles over two existing layers?

Practically no. Local roofers tear off at two layers because of weight, trapped moisture, hidden decking damage and warranty conditions. Confirm any code limit with your building department, but expect a full tear-off.

Is there cedar under my asphalt roof?

On pre-1950 Victoria, Oak Bay and Esquimalt homes, often yes. Check from the attic for cedar between the deck boards. If present, budget a plywood overlay on top of the extra tear-off.

Does a double layer make the roof sag?

It can add strain on older rafters and may contribute to a visible dip, which is one area a professional may inspect during tear-off. A sag that appeared suddenly needs assessment regardless of layers.

Sources

  1. Great Victoria Roofing pricing model (our estimate)Great Victoria Roofing, accessed 2026-09-10.
  2. Average roof replacement cost in BCGreen Building Canada (contractor/commercial estimate), accessed 2026-09-10.
  3. Census Profile, 2021 Census — period of constructionStatistics Canada, accessed 2026-09-10.
  4. Asphalt Roofing Manufacturers Association — residential resourcesARMA, accessed 2026-09-10.
  5. Building PermitsCity of Victoria, accessed 2026-09-10.

Full list with what each source supports: Sources · How we build estimates: Methodology

Last reviewed · Editorial team — reviewed against the sources listed on each page · Cost figures are estimates from our published pricing model, not quotations.

Request local roofing quotes

We share your details only with a local roofing provider you ask us to contact. No spam, no call lists.

Take the next step with confidence

About 60 seconds. Greater Victoria pricing. No sign-up.